Completion of the Corazon Creek Technical High School Building, Corazon Creek Village, Toledo District, Belize.
Description:
The contract proposes to:
The contract proposes to complete the construction of an incomplete single storey reinforced concrete structure
measuring 164’-11” long by 42’-2” wide complete with a proposed four (4) classrooms, office spaces, two (2) male
and female students’ bathrooms, two (2) male and female teachers’ lavatories, storage spaces, and an access ramp
to accommodate users with disabilities.
Works shall include but not be limited to the following activities: construction of a reinforced concrete floor slab;
construction of masonry walls; construction of reinforced concrete columns and beams; construction of a reinforced
concrete roof; application of concrete rendering; construction of ceilings; installation of windows and doors;
installation of electrical, plumbing, water supply and wastewater systems; application of surface finishes; and the
undertaking of landscaping activities. Adherence to the contract’s environmental and safety protocols during
construction is of paramount importance.